Sample deliverable

This is what comes back.

One plan sheet, worked all the way through to a bid package. Eight tabs, prepared for a named contractor. Same document you get on your own job. Read it here, or take the PDF if you just want to look and the workbook if you want to work in it.

This is a sample on a fictional project, prepared for a fictional contractor. It is not a real client, a real bid, or a record of work I have done — it says so on every tab. What it does show is the exact format, depth and discipline you get. Every quantity below is genuinely measured off the sheet shown underneath it. Nothing here is a made-up number, which is the entire point.

SINGLE SOURCE PROJECTS Preconstruction Bid Package
Prepared forSample Contractor LLC
ProjectNorthbank Commerce Park — Phase 2
TradeFence — perimeter chain link
Prepared bySingle Source Projects

That header prints at the top of all eight tabs — not just a cover page. Print any single sheet and it still says who it was prepared for.

  • Plan
  • Takeoff
  • Material list
  • Scope
  • Exclusions
  • Clarifications
  • RFQ / bid support
STAGE 01 — THE PLAN

What I get sent

A civil sheet with a fence line on it. 618′ × 428′ commercial parcel, perimeter fence on three sides, two gates, and a specification that does not entirely agree with the details. Normal Tuesday.

Sample civil site plan sheet C-3.0 showing a 618 by 428 foot parcel with perimeter chain link fence on three sides, a 24 foot double swing vehicle gate on the south line and a 4 foot man gate on the east line, with dimensions.

Sheet C-3.0 · 1" = 60′ · sample drawing, fictional project

STAGE 02 — THE TAKEOFF

Quantities, each one traced back to the drawing

Every line carries the sheet it came off and whether it was measured, counted or calculated. That is what lets you check the work in ten minutes instead of trusting it. Anything the documents do not settle is flagged VERIFY and gets a matching question — it never gets filled in with a guess.

ItemDescriptionQtyUnitConfidenceSourceBasis / assumption
0016′ galvanized chain link fabric, 9 ga., 2" mesh1,636LFMeasuredC-3.0618 + 200 + 224 + 300 + 294 — gate openings deducted
003Line posts, 2-3/8" O.D. SS40, at 10′-0" o.c.160EADerivedC-3.0 / spec 32 31 13Per run, ceil(length ÷ 10) − 1: 61 + 19 + 22 + 29 + 29
004Terminal, corner, end and gate posts, 3" O.D.8EACountedC-3.02 end + 2 corner + 4 gate posts
009Post footings — line posts, 10" dia. × 30" deep8.1CYVERIFYspec 32 31 13Detail 4/C-5.1 shows 24", the spec says 30". Priced to the spec. See clarification 001.
011Footing concrete, order quantity9.7CYDeriveditems 009 + 0108.78 CY neat + 10% waste — the waste factor is an assumption, set it to yours
012Post caps, tension bars, bands, rail ends, ties1LSAllowancespec 32 31 13Carried as a lump sum, not counted. The supplier schedules it against the post counts.
0133-strand barbed wire with extension arms0LFVERIFYdetail 4/C-5.1Not carried. Shown in a detail, absent from the spec, may be restricted by code. See clarification 002.

13 lines in the full workbook. This is a selection.

STAGE 03 — THE MATERIAL LIST

Order quantities, at the grade the spec calls for

Not just measurements — rolls, sticks and cubic yards, rounded the way you actually buy them, with the waste factor stated rather than buried. No prices anywhere on this tab, because none of them came from a quote I hold. Those go to the RFQ list instead.

ItemMaterialQtyUnitFromNote
M01Chain link fabric, 6′ × 9 ga., 2" mesh, galvanized33ROLLTakeoff 00250′ rolls covering 1,636 LF — 14 LF spare
M02Line post, 2-3/8" O.D. SS40, 8′-6"160EATakeoff 003Length assumes 6′ fence + 30" embedment. Revisit if clarification 001 changes the depth.
M03Terminal / corner / gate post, 3" O.D. SS40, 9′-0"8EATakeoff 004Length assumes 6′ fence + 36" embedment
M04Top rail, 1-5/8" O.D. galvanized78EATakeoff 00521′ sticks, sleeved
M08Concrete, 3000 psi, post footings9.7CYTakeoff 011Includes 10% waste — your factor may differ
M09Fittings package1LSTakeoff 012Allowance — supplier schedules against post and gate counts
STAGE 04 — THE SCOPE OF WORK

Split by how certain the documents actually are

Three bands, not one list. The middle band is the one that matters — work the documents imply but never state. That is where a bid quietly goes light, and it is a judgement call that belongs in front of you, not buried in an assumption.

Included — 7 items

  • 1,636 LF of 6′ galvanized chain link — fabric, line posts, terminal posts, top rail
  • One 24′ double swing vehicle gate with drop rod and cane bolts
  • One 4′ single swing man gate with latch and keeper
  • Concrete post footings at line, terminal, corner and gate posts
  • Bottom tension wire, continuous
  • Standard fittings, caps, bands, tension bars and ties
  • Cleanup and removal of my own debris

Potentially required — decide before you bid

  • Layout from corner stakes. The fence is drawn to the property line but the documents never assign who sets the corners.
  • Nominal grade following where the fence crosses the entry drive apron. No spot elevations are given along the alignment.
  • Longer line posts if clarification 001 resolves the footing depth deeper than the spec's 30".
  • Heavier gate posts and hardware if the vehicle gate is later required to accept an operator. None is shown, but the opening is at the site entry.
STAGE 05 — THE EXCLUSIONS

Sixteen of them, and every one says why

An exclusion you did not write down is a scope you agreed to. But an exclusion with no reason behind it is one the GC will argue you straight out of. So every row on this tab is grounded in what the documents say — or in what they conspicuously do not. “Commonly excluded” is not a reason, and my own quality gate rejects it.

Excluded itemReferenceWhy it is excluded
Property line survey, staking and boundary determinationC-3.0The fence is drawn to a property line, but no survey, monuments or staking responsibility appear on the civil sheet, and boundary determination is outside spec 32 31 13.
Gate operators, conduit, wiring, power, disconnectsC-3.0Both gates are drawn as manual swing gates. No operator, conduit, electrical service or pedestal appears at either gate location.
Rock or unsuitable soil excavation at post holesno geotech providedNo geotechnical report was included. The bid assumes augerable soil to footing depth, stated as an assumption on the scope tab.
Barbed wire and 45° extension armsdetail 4/C-5.1Shown in the detail but absent from the spec, and its use may be restricted at this occupancy. Excluded pending clarification 002 rather than assumed either way.
Bonds, prevailing wage, above-standard insurancefront-end not providedDivision 01 and the front-end documents were not in the set, so these requirements are unknown. See clarification 004.
Temporary construction fenceC-3.0Only permanent perimeter fence is shown. No temporary fence, phasing plan or traffic control appears on the sheet provided.

6 of 16 shown. The full list is in the workbook.

STAGE 06 — THE CLARIFICATIONS

What the drawings could not answer

Four questions came out of one fence sheet. Each carries what I assumed in the meantime and what changes if the answer is different — so it is a decision you can price, not a disclaimer you have to interpret.

#Sheet / specThe questionAssumed meantimeIf the answer is different
001spec 32 31 13 vs detail 4/C-5.1Line post footing depth — the spec says 30", the detail shows 24". Which governs?Priced to the spec at 30"; takeoff line 009 flagged VERIFYDropping to 24" takes about 1.6 CY of concrete out, and the labour with it
002detail 4/C-5.1The detail shows 45° extension arms with 3-strand barbed wire. The spec never mentions it, and code may restrict it here. In or out?Not carried. Excluded in writing.Adding it is roughly 1,636 LF of barbed wire plus 168 arms, plus labour
003C-3.0No fence line grade or spot elevations. Is the line within 6" of level over a 10′ bay, or does it need stepping or racking?Nominal grade following, no stepping. Stated as an assumption.Stepped or racked installation is materially slower and changes post lengths and fabric waste
004front-end docs (not provided)Bonds, prevailing wage, or above-standard insurance required?All three excluded in writing.Any of the three adds real cost plus administration that has to be inside your number
STAGE 07 — RFQ AND BID SUPPORT

What you still have to price before you submit

The material list turned into requests a vendor can actually quote, with the trap on each one called out. Anything on this tab is a number I do not hold and will not invent.

#What to quoteTypeQuantity / specWhat to watch
R01Complete chain link material packageMaterial1,636 LF · spec 32 31 13Ask for the fittings package broken out separately so it can be checked against the post counts
R02Gates — 24′ double swing and 4′ man gateMaterial2 EA, 6′ high, galvanizedConfirm lead time. Gates are usually the long pole on a fence job.
R03Ready-mix concrete, 3000 psiMaterial9.7 CYAsk about short-load fees — this is several small pours, not one truck
R05Barbed wire and extension arms — HOLDMaterial1,636 LF + 168 arms if requiredDo not send until clarification 002 is answered. Priced as zero today.

One more tab, and it is the whole philosophy

There is an eighth tab — Direct Cost — and every unit cost cell on it is empty. Not because I ran out of time. Because I do not hold a quote for any of them, and I will not type a number I cannot stand behind into a document you are going to bid off.

It carries the cost structure — labour, material, equipment, subs, other — and stops at direct cost. Overhead, markup, contingency and your selling price are yours. The tab says so in writing.

Your rates, your markup, your number, your name on the bid. I do the two days of work that comes before it.

Now do it with your job.

Send the next set on your desk. $99 for the first one, no contract, and you will know in three business days whether this is worth using again.